Lead times and support
Injection Molding Lead Times You Can Plan Around
A quote in 1 to 2 working days, T1 samples in about 3 to 4 weeks for a simple mold and 4 to 6 weeks for a complex one, and first runs below 5,000 pieces about a week after you approve the samples. Molds are built and corrected in our own Dongguan toolroom, so changes do not wait on an outside shop.
- 1–2 daysDFM and quote, working days
- 3–6 weeksdrawing approval to T1
- ~1 weekfirst run under 5,000 pcs

When timing matters most
Buyers who ask us about lead time first
If one of these sounds like your project, put the date in your RFQ and we plan the build back from it.
A fixed launch date
Retail, trade show or customer delivery that cannot move.
A supplier that let you down
Late samples or slow repairs elsewhere, and no time to lose twice.
A program with reorders
You need to know how fast repeat lots can follow the first one.
Samples for testing
Fit, drop or certification tests are booked, and parts must arrive first.
Timeline
Injection molding lead time, stage by stage
These are our usual figures. Your quotation states the dates for your own part, and the dated plan shows each step.
| Stage | Usual time | What decides it | What you receive |
|---|---|---|---|
| Your RFQ | Within 24 hours on working days | How complete the drawing and volume data are | First questions or a first estimate |
| DFM and quote | 1–2 working days | Part complexity, open design questions | Free DFM report; mold and part priced separately; dated plan |
| Mold build to T1 | 3–4 weeks simple · 4–6 weeks complex | Slides and lifters, hot runner, cavity count, polish or texture | T1 samples at no charge, with measurement report |
| Corrections | About 1 week for a simple change | What the T1 measurement shows | Corrected samples, measured again |
| First production | About 1 week after approval, below 5,000 pcs | Order size, resin and finishing steps | Parts checked against the signed sample |
| Shipping | Depends on route and destination | Sea, air or express; customs at your end | Export packing in cartons, on pallets or in wooden crates |
Swipe the table to see every column →
Expert view
Why one mold takes 3 weeks and another takes 6
Mold lead time is set mostly by the part, not by how hard the toolroom works. These features add machining, fitting and trial time:
- Slides and lifters for undercuts each add parts to machine and fit
- Hot runner systems add a manifold, nozzles and wiring to install and test
- More cavities mean more inserts to cut and balance
- Mirror polish or texture adds finishing, and texture is often done after T1
- Design changes after steel is cut restart part of the work
How to save time
The fastest week is the one you do not repeat
Most delays we see come from a second correction loop, not from the first build. Settling wall thickness, draft, undercuts and the visible faces in DFM before steel is cut is the most reliable way to keep the T1 date.
Send a STEP file, the 2D drawing with tolerances, the resin, the first order quantity and your target date. With that, the quote names the steel, cavity count and the plan dates.
What goes wrong with timing
Four delays buyers fear, and how we prevent each
After delivery
Support after your mold and parts are delivered
Here is what continues after the first shipment.
Mold repairs
Done in our own toolroom, with a simple change taking about one week.
Files and spares
Drawings, process sheet, spares and electrodes as listed, if the mold moves to your plant.
Out-of-tolerance results
Handled step by step, and nothing on the part, tool or resin changes without your approval. See how.
Repeat orders
Run on the approved process sheet and checked against the signed sample.
How a lot that fails inspection is replaced or credited is agreed in each quotation, so you see the terms before you order.
Terms at a glance
Commercial terms that affect your schedule
Related pages
Plan the rest of your project
FAQ
Questions about lead time and support
How long does it take to make an injection mold?
From drawing approval to T1 samples, a simple mold takes about 3 to 4 weeks in our toolroom and a complex one about 4 to 6 weeks. Slides, hot runners, cavity count and surface finish decide where your mold falls.
When do production parts ship after the mold is approved?
Orders below 5,000 pieces usually leave the factory about one week after you approve the samples. Larger runs are scheduled in the quotation against our 15 presses.
What happens if the T1 samples need corrections?
We correct the mold in our own toolroom, so there is no wait for an outside shop. A simple correction takes about one week, then the next samples are measured again.
Can you speed up the first mold?
The biggest saving comes before steel is cut: a settled design and a free DFM review avoid a second correction loop. Tell us your launch date in the RFQ and we plan the mold build back from it.
How will we know where the project stands?
You get a dated plan with the quote, covering DFM, 3D mold review, steel, T1, corrections, sample sign-off and first run. Maggie is your single contact and answers within 24 hours on working days.
What support do we get after the mold is delivered?
Repairs and changes are done in our own toolroom. If the mold goes to your plant, the drawings, process sheet, spares and electrodes listed in the order go with it, so your team can maintain it.
Send your drawing with the date you need parts
We reply within 24 hours on working days and send the quote with a dated plan in 1 to 2 working days.